BESS~Solar~ Hybrid~PHS- Why RTC & FDRE Projects faces an existential crisis ? Is Solar with BESS going to be the future for Discom?

India’s renewable energy (RE) tendering is shifting from high-volume, fixed targets (73 GW in 2024) to a focus on Round-the-Clock (RTC) supply, Firm and Dispatchable Renewable Energy (FDRE), and storage-integrated projects. While 2024 set records, 2025 has seen a slowdown in new tender volumes due to unsold capacity.

Key Tendering Trends in India (2025-2026):
Focus on Hybrid & Storage: Tenders are increasingly demanding RTC and FDRE to ensure 24/7 power availability, using Battery Energy Storage Systems (BESS). Solar integrated with storage projects.

Declining Storage Tariffs: Tariffs for renewables with storage dropped by 9% in Q3 2025, driven by falling battery costs, making storage-backed projects more competitive.
Capacity Crunch & Slowdown: Over 42 GW of tendered capacity is currently without buyers (unsigned Power Supply Agreements - PSAs) as of late 2025, causing a slowdown in new tender activity in early 2025.

Shift in Strategy: The government is moving away from rigid annual tender targets, planning to issue tenders based on actual demand from state utilities rather than a fixed 50 GW goal.

Key terms

•BESS (Battery Energy Storage System): Uses batteries (typically lithium-ion) to store electricity and discharge it when needed. It is known for near-instantaneous response times, making it ideal for frequency regulation and peak load shaving.

•PHS (Pumped Hydro Storage): A form of energy storage that uses two water reservoirs at different elevations. During surplus energy, water is pumped to the higher reservoir; during peak demand, it is released through turbines to generate power. It is currently the most widely used large-scale storage solution in India

Project & Tender Models (Application)

These define how technologies are combined and the contractual obligations for power delivery.

  • Hybrid: A project that combines two or more renewable sources, such as solar and wind, at a single location. The goal is to increase the Capacity Utilization Factor (CUF) by leveraging complementary generation profiles (e.g., solar during the day, wind at night).

  • RTC (Round-the-Clock): A tender model that requires developers to provide a continuous, guaranteed supply of power 24/7. To meet these strict availability requirements, developers must integrate storage (BESS or PHS) or bundle renewable energy with thermal power.

  • FDRE (Firm and Dispatchable Renewable Energy): A newer, demand-profile-driven tender designed to match the specific consumption patterns of distribution companies (DISCOMs). Unlike RTC, which aims for a flat 24/7 supply, FDRE requires “firm” delivery during specified hours (like evening peaks) to mimic the reliability of traditional coal plants.

Key Differences

Feature Hybrid RTC FDRE
Primary Goal Maximize infrastructure use Continuous 24/7 power Firm power matching demand
Storage Role Optional Essential (BESS/PHS) Essential (BESS/PHS)
Flexibility High (Supply-driven) Low (Constant supply) High (Demand-driven)
Typical CUF 35% - 50% ~80% High (80%+)

Would you like to compare the latest tariff rates discovered in recent auctions for these different project types?

FDRE/RTC Tariffs have risen to ₹5.00 – ₹5.07/kWh , approaching new thermal power costs.

Solar + BESS Tariffs have been discovered at ~₹3.53/kWh , offering a 30% cost saving while effectively solving the DISCOMs’ most pressing problem: evening peak deficits.

While RTC and FDRE define the contractual requirement, BESS defines the physical solution for achieving 24/7, flexible, green power.

The cost factor is the only reason ehy DISCOMs are Not Signing FDRE and RTC PPAs and opting for standalone Solar - BESS

So RTC & FDRE projects have strong competition from stand alone Solar plus BESS, which Discom’s are opting for.

https://etedge-insights.com/industry/energy/the-midnight-sun-rtc-is-the-industrialization-of-renewables-and-the-path-to-energy-sovereignty/

Discl. For educational purpose only

6 Likes
1 Like

KPI GREEN ENERGY: CO’S UNIT SIGNS BESPA WITH GUVNL FOR 445 MW / 890 MWH BESS PROJECTS

2 Likes

A Thermal Mimic Renewable Tender (RTC-TM) is a type of power procurement where renewable energy projects are designed to behave like a thermal power plant in terms of reliability and continuous supply. It is increasingly used by agencies like Solar Energy Corporation of India to ensure stable electricity while expanding renewable energy capacity

2 Likes

India’s energy storage market in 2025 & 2026 BESS Vs pumped Storage

India’s energy storage system (ESS) market grew from 122GWh to 224GWh cumulative, a 1.8X times increase year-over-year (YoY), with a total of 60GWh projects under execution, 80GWh under various stages of tendering and 35GWh under the awarded stage.

India's energy storage market in 2025: From tenders to scaled deployment - Energy-Storage.News.

Source: LinkedIn Energy Storage: The Real Question is Not PSP vs BESS ——————————————— Yesterday we reviewed the Pumped Storage Projects (PSPs) in pipeline in Rajasthan. Our discussion was highlighted by familiar… | Ajitabh Sharma, IAS | 60 comments

Source: LinkedIn Pumped Storage vs. BESS: A Comprehensive Comparison for Grid Stability

1 Like

Can Solar plus BESS beat HVDC transmission ?

As of March 2026, the use of Solar plus Battery Energy Storage Systems (BESS) as an alternative to High-Voltage Direct Current (HVDC) transmission is gaining significant traction, particularly in India

. Major recent developments indicate that BESS is being actively evaluated and, in some cases, prioritized over traditional long-distance transmission infrastructure due to lower costs, shorter gestation periods, and enhanced grid flexibility. [1, 2]

Key Recent Developments (2025–2026)

  • Rajasthan Evaluation Study: In 2025, India’s National Committee on Transmission (NCT) conducted a landmark study evaluating BESS as an alternative to a major HVDC transmission line for Rajasthan’s solar zones.

    • Cost Advantage: An HVDC link was estimated to cost between ₹25,261 crore and ₹34,814 crore, whereas a 6 GW BESS alternative was projected at approximately ₹21,675 crore.

    • Decision: While the NCT initially opted for HVDC for the Barmer-II project in mid-2025, it mandated that BESS must be considered as an alternative for all future high-renewable evacuation schemes due to its flexibility and lower implementation challenges.

  • Massive BESS Tenders and VGF: The Ministry of Power has released the second tranche of Viability Gap Funding (VGF) to support 30 GWh of standalone BESS capacity as of January 2026.

  • Adani’s Strategic Entry: Adani announced plans for one of the world’s largest single-location BESS projects (1,126 MW / 3,530 MWh), scheduled for commissioning by March 2026.

  • Tamil Nadu Deployments: In March 2026, the Tamil Nadu Green Energy Corporation (TNGECL) received approval for a tariff of ₹4.47/kWh for solar-plus-BESS projects, which is significantly lower than previous estimates.

Comparison: BESS vs. HVDC Transmission

Featurers Solar + BESS Alternative HVDC Transmission Line
Primary Function Stores excess solar for peak/night use; provides local grid stability. Transports power over long distances (>500 km) with minimal losses.
Gestation Period Considerably shorter (typically 1–2 years). Long (often 4–6+ years) due to land acquisition and complex engineering.
Cost Trends Costs are plummeting (from ₹10.18 to ₹2.1 per unit in some cases). High initial capital for converter stations; lower long-term maintenance.
Grid Impact Enhances flexibility; helps avoid backing down thermal plants. Increases system strength and connects asynchronous grids.

Why BESS is Replacing HVDC in Recent Planning

  • Flexibility & Resource Adequacy: BESS allows solar energy to be “shifted” to evening peak hours, providing resource adequacy without requiring massive new transmission lines to distant load centers.

  • Grid Stability (Duck Curve): BESS is increasingly preferred for handling the “duck curve” (fast ramping requirements when solar production drops) by injecting power quickly, which is more agile than traditional transmission switching.

  • Reduced Land & Right-of-Way Issues: Unlike HVDC lines that require extensive land corridors, BESS can be co-located at existing substations or solar farms.

  • However , the HVDC transmission infra is a long term solution to long distance transmission and energy transmission and given our geographical spread of our country and therefore HVDC companies would likely to grow at its own pace.

HVDC transmission stocks are primarily driven by massive grid modernization projects and renewable energy integration. Key players in India and globally include Power Grid Corporation of India, Hitachi Energy, GE T&D India, Siemens, and Adani Energy Solutions, which are benefiting from high-value infrastructure upgrades and long-distance, high-capacity power lines.

Further some of these HVDC transmission companies that specialize in High Voltage Direct Current (HVDC) technology also heavily deal with Battery Energy Storage System (BESS) integration into the Grid.

Companies like Hitachi Energy, Siemens Energy, and General Electric (GE), leverage their expertise in power electronics to provide integrated solutions that improve grid stability, especially when integrating renewable energy.

Discl : This article is AI generated for purely educational purpose. Not a buy or sell recommendation on any BESS or HVDC stocks. Please do your own assessment before any kind of investment or disinvestment!

3 Likes

ACME Solar Holdings Ltd commissioned the second phase of 33.335 MW/160.51 MWh out of 300 MW/1409.34 MWh capacity of Battery Energy Storage System (BESS) Project

2 Likes

#Pumped Storage Hydro power ( PSH) vs conventional Hydropower- Types of Hybrids in Renewable energy

Conventional hydropower generates electricity from flowing water (rivers/dams) to meet base or peak demand, while pumped storage hydropower (PSH) functions as a “water battery” by recycling water between reservoirs, pumping it uphill during low demand and releasing it during high demand. PSH supports grid stability with storage of renewables, whereas conventional hydro is a direct renewable generator.

PSH also known as PSP (pumped Storage system)

Key Comparisons:

  • Operation: Conventional hydro moves water one way (downstream), while PSH moves water in both directions, reusing the same water supply.

  • Purpose: Conventional hydro is primary generation; PSH is utility-scale storage.

  • Energy Source: Conventional hydro relies on river flow (renewable). PSH requires external electricity to pump water up, serving as an energy storage solution.

  • Grid Role: PSH provides fast, large-scale storage to balance intermittent renewables (wind/solar), while conventional hydro often provides baseload or peaking power.

  • Environmental Impact: Conventional dams impact river ecosystems significantly. PSH, particularly closed-loop systems, can have a lower ecological impact

Various types of Hybrids in renewables

Solar + wind

Solar + Hydro

Wind + hydro

Solar + wind +Hydro

Any one of the above renewable or its combination can also accompany with BESS as energy storage.

Solar + BESS

Wind + BESS

Solar + wind + BESS

Solar + wind + Hydro + BESS

Which hybrid is very popular for now is Solar + Wind + BESS.

Most economical stand alone source is Solar with BESS which is also very.popular

Discl : purely For educational purpose only. Not a buy or sell recommendation for any kind of renewable stocks

2 Likes





PACE DIGITEK: BESS BUSINESS – KEY TAKEAWAYS

Emerging as a key player in Battery Energy Storage Systems (BESS)
Delivered ~400 MWh; ~200 MWh already operational
Order book: ~₹6,000 Cr (target ~₹10,000 Cr by Mar’26)
Additional pipeline: ~₹4,000 Cr

CAPACITY EXPANSION

  • Current: 2.5 GWh → 5 GWh (Mar’26) → 10 GWh (Sep’26)
  • FY27 effective production target: ~7.5 GWh

It’s an end-to-end BESS player: packs → racks → containers → EPC
It Does NOT manufacture cells (imports from global suppliers).
it is Expanding into container manufacturing (backward integration).
An indirect proxy to data center & energy infra growth
Beneficiary of rising demand for storage, backup & grid stability
Strong growth visibility backed by scale-up & structural BESS demand

3 Likes