FY22Q3 concall notes:

  • Pipavav: LPG jetty work for handling VLGC is expected to completed by June 2022 (extended from April 2022)
  • Kandla: Targeting 1 MT gas volumes in first year of operations (assuming commercialization goes smoothly)
  • Haldia: Recovered significant volume due to HPCL ramp up, should be back to pre BPCL exit volumes in 2 quarters (revised from earlier guidance of March 2023)
  • Mumbai: Current throughput capacity is only 1.1 MTPA, this will increase to 1.5 MTPA only in FY23
  • Autogas division: Not happy with the current volumes and want to improve it, EBITDA margins have been maintained at 10’000/ton
  • Liquid division margins largely vary b/w 65-70% (depending on the kind of liquids stored)