For now the only caution is lack of transparency at the managements end to not give any updates on phase 1 expansion which was delayed to January end. Some credible sources say it may not go live for another 3-4 months.
Since the Unit 3 expansion stands delayed, I have few questions:
Phase 1 - It was supposed to become operational by Oct - Nov 2025. In 4-5 months of operation, this was supposed to do ~60 crs of sales. Do we have any fresh update regarding the commencement of this phase? 2400 tons, ~INR 700 realization - gives ~170-175 crs of sales. Is this correct?
Phase 2 - This phase was supposed to become operational by June-July 2026. Any update on this as well. We are running on track here?
Rating agency - CRISIL on Feb 27, 2026 mentions that issuer is not co-operating. 1 month later, CARE upgrades the rating. If anyone has access to the rating rationale of CARE, plz share.